Project Duration
Stipulated Date of Commencement
January 30 2019
Stipulated Date of Completion /
Likely Date of Completion August 08 2019
Likely Date of Completion August 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,855,739.30
Awarded for
₹ 6,238,708.29
Project highlights
Repairs/Ugradation & Maintenance of Government Schools in the Sate of Goa – Bardez Taluka
-GPS Bamburdem Moira, GPS St. Cruz Bastora.
Contractors
M/s. R.G. Contractors & Engineers
Consultants
M/s. Intrinsic Classics