Project Duration
Stipulated Date of Commencement
November 30 2014
Stipulated Date of Completion /
Likely Date of Completion May 30 2015
Likely Date of Completion May 30 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,385,911.40
Awarded for
₹ 16,443,238.00
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Bhasker Wagle & Associates