Project Duration
Stipulated Date of Commencement
October 17 2022
Stipulated Date of Completion /
Likely Date of Completion December 26 2022
Likely Date of Completion December 26 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,102,103.03
Awarded for
₹ 5,110,508.00
Contractors
M/s. AAI Jee Interior
Consultants
M/s. Bhaskar Wagle and Associates.