Project Duration
Stipulated Date of Commencement
July 09 2018
Stipulated Date of Completion /
Likely Date of Completion March 23 2019
Likely Date of Completion March 23 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 76,32,086.00
Awarded for
₹ 8,291,245.31
Project highlights
Repairs/Upgradation & Maintenance of Government School
Contractors
M/s.Atharva Infra Solutions
Consultants
M/s. Vaishali Pednekar Associates