Project Duration
Stipulated Date of Commencement
September 24 2021
Stipulated Date of Completion /
Likely Date of Completion April 03 2022
Likely Date of Completion April 03 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,400,460.00
Awarded for
₹ 6,182,568.82
Project highlights
Repairs & Maintenance of Government schools of Bicholim Taluka
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Vaishali Pednekar Associates