Project Duration
Stipulated Date of Commencement
September 24 2021
Stipulated Date of Completion /
Likely Date of Completion April 03 2022
Likely Date of Completion April 03 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,400,460.00
Awarded for
₹ 6,182,568.82
Project highlights
Repairs & Maintenance of Government schools of Bicholim Taluka
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – GHS Xeldem, Quepem Taluka
View Project
Repairs/Upgradation and Maintenance of Government High school at Kalay in the Sanguem taluka
View Project
Repairs & Upgradation of Government High schools in State of Goa- Quepem Taluka (Package A)
View Project