Project Duration
Stipulated Date of Commencement
January 22 2019
Stipulated Date of Completion /
Likely Date of Completion July 21 2019
Likely Date of Completion July 21 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,740,455.00
Awarded for
₹ 10,889,310.58
Project highlights
Repairs/Upgradation & Maintenance of Government Schools
Contractors
M/s. Sirajuddin beig
Consultants
M/s. Bhaskar Wagle & Associates
See Similar Projects
Construction of Anganwadi Centres from NABARD Assistance – Package VII (GPS Bethoda).
View Project
Construction of Swimming Pool at Sankhali.
View Project
Repairs/Ugradation & Maintenance of Government Schools in the Sate of Goa – Bardez Taluka -GPS Bamburdem Moira, GPS St. Cruz Bastora.
View Project





