Project Duration
Stipulated Date of Commencement
September 26 2018
Stipulated Date of Completion /
Likely Date of Completion August 11 2019
Likely Date of Completion August 11 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 83,21,246.00
Awarded for
₹ 9,319,010.21
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works
Contractors
M/s.Joshi Constructions
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
Repairs/ Upgradation & Mainrenance ofGovemment Schools in the State ofGoa – Civil, Plumbing & Electrical works – Package – III (Tiswadi & Ponda Taluka) [Also falls in Ponda, St. Andre, Panaji and Cumbarjua]
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Package N – Sattari Taluka – GPS Nanus, GPS Zarme,GPS Dabem, GPS Kumthol, GPS Karanzol, GPS Karmali Budruk) – Balance works.
View Project
Repairs & Upgradation of Government Higher Secondary School Sanquelim.
View Project