Project Duration
Stipulated Date of Commencement
September 26 2018
Stipulated Date of Completion /
Likely Date of Completion August 11 2019
Likely Date of Completion August 11 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 83,21,246.00
Awarded for
₹ 9,319,010.21
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works
Contractors
M/s.Joshi Constructions
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
Repairs/Upgradation and maintenance of Government schools in the state of Goa – Package H (GPS Morlem Colony, GPS Pissurlem, GPS Deulwada Morlem, GPS Morlem)