Project Duration
Stipulated Date of Commencement November 15 2018
Stipulated Date of Completion /
Likely Date of Completion
August 15 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,968,423.00
Awarded for ₹ 13,587,959.00

Project highlights

Roofing work, Tilling work Painting , Repairing of window & doors,plumbing works, electrical works, etc.

 
Gallery Image
Contractors
M/s. Sri Sri Akruthi Projects Pvt. Ltd
Gallery Image
Consultants
M/s Bhaskar Wagle & Associates
 
Similar Projects

See Similar Projects

Similar Project

Repairs, Upgradation & Maintenance of Government Schools in the State of Goa – Packge O (Sattari Taluka) – (GPS, Gaonkarwada Vantem, GPS Vantem, GPS Advoi)

View Project
Similar Project

Construction of Higher Secondary School building for Dr.K.B.Hedgewar Higher Secondary School at Cujira, Bambolim,Tiswadi,Goa.

View Project
Similar Project

Infrastructure works for Sanjay Centre for Special Education at Bogda, Vasco – Electrical, Lift and Fire Fighting Works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.