Project Duration
Stipulated Date of Commencement
May 28 2019
Stipulated Date of Completion /
Likely Date of Completion November 11 2019
Likely Date of Completion November 11 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,083,775.00
Awarded for
₹ 4,528,391.98
Project highlights
Repair work of Schools.
Contractors
M/s. R.G.Contractors & Engineers
Consultants
M/s. Vaishali Pednekar Associates