Project Duration
Stipulated Date of Commencement
May 16 2016
Stipulated Date of Completion /
Likely Date of Completion August 15 2017
Likely Date of Completion August 15 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,047,588.00
Awarded for
₹ 13,619,639.35
Contractors
M/s.Vaishnavi Infrastructure
Consultants
M/s. Nitin Arolkar