Project Duration
Stipulated Date of Commencement
December 28 2016
Stipulated Date of Completion /
Likely Date of Completion March 27 2018
Likely Date of Completion March 27 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,360,906.00
Awarded for
₹ 15,541,411.51
Project highlights
The proposed Panchayat Building is to be built on plot area of 412.50 m2 on survey no. 44, Sub Division no. 9 in Cavellosim village, Salcete Taluka .it is G+1 structure. Consists of Panchayat building with office on ground floor and hall on First floor.
Contractors
M/s.Riffaath Constuction
Consultants
M/s.Datta Kare Associates