Project Duration
Stipulated Date of Commencement
January 30 2014
Stipulated Date of Completion /
Likely Date of Completion February 13 2014
Likely Date of Completion February 13 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,979,192.00
Awarded for
₹ 47,708,350.00
Project highlights
Hotmixing of road from District collectorate upto Agalli junction, Fatorda
Contractors
M/s.Ritesh Developers Pvt. Ltd
Consultants
M/s.Datta Kare Associates