Project Duration
Stipulated Date of Commencement December 19 2014
Stipulated Date of Completion /
Likely Date of Completion
December 18 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 326,394,633.00
Awarded for ₹ 383,810,938.44

Project highlights

The scope of construction, completion & maintenance during the defect liability period of “UPGRADATION & BEAUTIFICATION OF ROAD NETWORK FROM SERAULIM TO COLVA BEACH – PHASE I comprises of :
Construction of Culverts in the following stretches
Two Box culverts in the stretches between Seraulim Junction to Colva Junction
One Box Culvert between Colva Junction & Sernabatim
Construction of two Box Culverts between Khareband Bridge to Ville Karle
Construction of RCC Retaining walls with Service ducts in the following stretches:
Both side in the stretches between Seraulim Junction to Colva Junction
One side between Colva Junction & Sernabatim
Construction of service ducts in the land portion in the specific area
Both side in the stretches between Seraulim Junction to Colva Junction
One side between Colva Junction & Sernabatim
Cross drainage works (RCC works)

 
Gallery Image
Contractors
M/s. H. S. Mehta
Gallery Image
Consultants
M/s. Construma Consultancy Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Improvement / Hot mixing of roads in Arpora – Baga.

View Project
Similar Project

Uguem Bridge

View Project
Similar Project

Demolition Of Existing Bridge And Reconstruction Of Box Culvert On 18th June Road Over St. Inez Creek, Panaji -Illumination Work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.