Project Duration
Stipulated Date of Commencement
September 21 2018
Stipulated Date of Completion /
Likely Date of Completion December 21 2018
Likely Date of Completion December 21 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,292,381.00
Awarded for
₹ 9,083,500.00
Project highlights
The scope of work includes:
1) Supply, installation, testing & commissioning of 33 KV, 3CX400 sq. mm, underground armoured cable – 4078 meters.
2) Supply, installation, testing & commissioning of 11 KV, 3CX300 sq. mm, underground armoured cable – 108 meters.
3) Dismantling of HT/LT overhead lines and Installation of new 100kVA distribution transformer centre.
Contractors
M/s. Consistent Engineers
Consultants
M/s. Nitin Arolkar
See Similar Projects
Uguem Bridge
View Project
Supply, Installation, Testing and Commissioning of flag mast system at the new bridge across river Mandovi at Panaji, Goa
View Project
Construction of Bridge for local farmers to cross river stream for cultivation of fields from Chune – Kator to Vanso Field in Village of Cumbarjua.
View Project