Project Duration
Stipulated Date of Commencement
November 15 2005
Stipulated Date of Completion /
Likely Date of Completion December 15 2005
Likely Date of Completion December 15 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 611,117.00
Awarded for
₹ 641,000.00
Project highlights
The laying of paver blocks was taken up on the balance portion of the promenade on the riverside from Patto bridge to Miramar circle.
Contractors
M/s. D. K. Bhomkar
Consultants
M/s. Prabhugaonker & Associates
See Similar Projects
Construction of Bus Stand & Market Complex at Pernem – Erecting 11 kV overhead line from feeder at the Electricity Department Substation to the Bus Stand Substation
View Project
Construction of Bus Stand at Marcel, Goa – Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.
View Project
Khareband Bridge.
View Project





