Project Duration
Stipulated Date of Commencement
February 27 2014
Stipulated Date of Completion /
Likely Date of Completion April 27 2014
Likely Date of Completion April 27 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,232,612.00
Awarded for
₹ 9,932,510.00
Project highlights
The scope of work involves supply and installation of decorative street light poles on the Service road.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.