Project Duration
Stipulated Date of Commencement
October 31 2018
Stipulated Date of Completion /
Likely Date of Completion September 08 2019
Likely Date of Completion September 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,197,687.00
Awarded for
₹ 6,289,100.00
Project highlights
Relocation of Structures adjacent to the Main roads in Fatorda Constituency to ensure smooth flow of traffic
Contractors
M/s. Race Constructions
Consultants
M/s. Ankit Prabhudessai
Sub Works
This project involved 1 sub works. The details of the same available below
1
Widening of roads and relocation of structures in Fatorda Constituency – Phase II – Illumination of Footpath from Colva Circle to Ravindra Bhavan Circle at Fatorda, Margao, Goa
100% completed
Project Duration
Stipulated Date of Commencement
January 08 2018
Stipulated Date of Completion /
Likely Date of Completion January 22 2018
Likely Date of Completion January 22 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,181,939.00
Awarded for
₹ 3,492,794.00
Project highlights
Providing Streetlight Poles from Colva circle to Ravindra bhavan Circle.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. Ankit Prabhudessai
See Similar Projects
Supply, Installation, Testing and Commissioning of flag mast system at the new bridge across river Mandovi at Panaji, Goa
View Project
Construction of approaches to Cumbarjua bridge including road link upto Khandola college.
View Project
Construction of Bus Stand at Shiroda – Phase II : Civil works, internal electrification and road
View Project