Project Duration
Stipulated Date of Commencement February 22 2014
Stipulated Date of Completion /
Likely Date of Completion
April 07 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,345,568.00
Awarded for ₹ 28,150,235.00

Project highlights

Internal Roads of total approximate length of 5.7km hotmixed and widened at certain locations.

 
Gallery Image
Contractors
M/s. Shaurya Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Demolition of Old existing jetty and Reconstruction of New Captain of Ports jetty at Old Goa.

View Project
Similar Project

Construction of Training Wall & upgradation of fishing jetty at Cutbona (South Goa). (Revised Scope of work) Construction of fishing jetty at Cutbona (South Goa).

View Project
Similar Project

Widening and Improvement of MDR No.2 between chainage 3.40 Km to 9.12 Km from Merces to Goa Velha (Part).

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.