Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion April 07 2014
Likely Date of Completion April 07 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,345,568.00
Awarded for
₹ 28,150,235.00
Project highlights
Internal Roads of total approximate length of 5.7km hotmixed and widened at certain locations.
Contractors
M/s. Shaurya Construction Pvt. Ltd.
Consultants
M/s. Datta Kare Associates