Project Duration
Stipulated Date of Commencement
January 27 2014
Stipulated Date of Completion /
Likely Date of Completion March 12 2014
Likely Date of Completion March 12 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,764,402.00
Awarded for
₹ 42,038,215.00
Project highlights
Hotmixing of roads.
Contractors
M/s. Race Constructions,
Consultants
M/s. Madhav Kamat & Associates