Project Duration
Stipulated Date of Commencement
May 26 2006
Stipulated Date of Completion /
Likely Date of Completion August 25 2006
Likely Date of Completion August 25 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 36,482,879.00
Awarded for
₹ 44,187,674.21
Project highlights
Hot mixing (laying of bituminous macadam and asphaltic concrete), lane marking, construction of culverts, providing gutters and cross drainages wherever required. The approximate length of the road is around 5.72 kms.
Contractors
M/s. Assmas Constructions Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates