Project Duration
Stipulated Date of Commencement
April 26 2007
Stipulated Date of Completion /
Likely Date of Completion October 25 2007
Likely Date of Completion October 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,644,386.00
Awarded for
₹ 34,552,373.00
Contractors
M/s. Kirloskar Constructions & Engineers Limited
Consultants
M/s. Construma Consultancy Pvt. Ltd.
Sub Works
This project involved 2 sub works. The details of the same available below
1
Construction of Jetty at Brittona – Additional works.
100% completed
Project Duration
Stipulated Date of Commencement
July 16 2010
Stipulated Date of Completion /
Likely Date of Completion October 15 2010
Likely Date of Completion October 15 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,985,905.00
Awarded for
₹ 2,183,970.00
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Vijaykumar Sawant Associates
2
Construction of Jetty at Brittona – Additional electrical works
100% completed
Project Duration
Stipulated Date of Commencement
April 06 2010
Stipulated Date of Completion /
Likely Date of Completion June 05 2010
Likely Date of Completion June 05 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 609,064.00
Awarded for
₹ 651,172.00
Contractors
M/s. Oman Enterprises
Consultants
In-house (GSIDC)
See Similar Projects
Beautifcation of road from Sanvordem circle to Capxem.
View Project
Construction and upgradation of fishing jetty at Malim (North Goa) and Cortalim (South Goa).
View Project
Pedestrian Bridge Linking Central Library & Creek – Dynan Setu
View Project





