Project Duration
Stipulated Date of Commencement
April 28 2010
Stipulated Date of Completion /
Likely Date of Completion October 27 2011
Likely Date of Completion October 27 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 174,633,507.09
Awarded for
₹ 185,911,708.00
Project highlights
Bridge across tributary of river Chapora connecting villages Ozari and Tharmas.
Contractors
M/s. Aditya Construction Company
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.
See Similar Projects
Construction of Pedestrian Arch Bridge connecting Mandovi River Promenade and DB Road, over St. Inez Creek near ESG Building at Panaji
View Project
Design and Construction of bridge at Patto in Panaji including approach roads
View Project
Uguem Bridge
View Project