Project Duration
Stipulated Date of Commencement
April 28 2010
Stipulated Date of Completion /
Likely Date of Completion October 27 2011
Likely Date of Completion October 27 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 174,633,507.09
Awarded for
₹ 185,911,708.00
Project highlights
Bridge across tributary of river Chapora connecting villages Ozari and Tharmas.
Contractors
M/s. Aditya Construction Company
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.
See Similar Projects
Construction of Bus Stand at Valpoi.
View Project
Construction of Bridge at Dando Mollo in village panchayat Velsao-Pale in Cortalim constituency
View Project
Construction of Codal – Derodem bridge including approaches.
View Project





