Project Duration
Stipulated Date of Commencement April 28 2010
Stipulated Date of Completion /
Likely Date of Completion
October 27 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 174,633,507.09
Awarded for ₹ 185,911,708.00

Project highlights

Bridge across tributary of river Chapora connecting villages Ozari and Tharmas.

 
Gallery Image
Contractors
M/s. Aditya Construction Company
Gallery Image
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of Road Bridge at Balli in Quepem Constituency on Balli – Fatorpa MDR Road at Balli in Quepem.

View Project
Similar Project

Hot mixing & Improvement of Internal Roads in V. P. Navelim in Navelim Constituency.

View Project
Similar Project

Providing and applying high build, crack building, electromeric, protective and waterproof coating to the Grade separator (2 flyovers) at Dabolim airport.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.