Project Duration
Stipulated Date of Commencement May 22 2003
Stipulated Date of Completion /
Likely Date of Completion
November 21 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 91,123,000.00
Awarded for ₹ 87,900,000.00

Project highlights

• Length : 150 m, width : 12 m.
• Length of clear navigational span : 65 m.
• Carriage way width: 7.5 m.
• Width of footpaths with paver block : 1.50 m.
• Length of approach on Pirna side : 200 m and on Ozorim side : 450 m.
• Electric poles with fixtures on the bridge and approaches.
• The bridge serves as a connection to the Ozorim and Pirna village.
• The bridge has reduced the distance from Pirna to Pernem by 15 kms

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. TPF Engineering Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Dismantling of HT overhead lines and supplying & laying of HT Underground cables at Panjim – HT Cable work from EDC Substation to Chimbel junction – Additional Work

View Project
Similar Project

Supply, Installation, Testing and Commissioning of flag mast system at the new bridge across river Mandovi at Panaji, Goa

View Project
Similar Project

Improvement and Upgradation of road network from MDLB Hospital to Baina Sea Shore, Shafi Masjid to Baina Recreational Club, Bharat lines to Headland Sada Junction in Mormugao Constituency.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.