Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion September 07 2020
Likely Date of Completion September 07 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 127,712,059.00
Awarded for
₹ 138,447,777.00
Project highlights
The projects includes demolition and reconstrcution of market complex at Bhoma , Adcolna . The proposed building has a total of 60 shops, separate spaces for the vegetable vendors and fish and meat vendors. A community hall of a total capacity 450 people.
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. Shiva Consultancy Services Pvt. Ltd.
See Similar Projects
Electrical Work
View Project
Supply, Installation, Testing and Commissioning of street light poles and fixtures along with allied electrical works for the stretch from Odxel junction to GMC
View Project
External Lighting Works
View Project





