Project Duration
Stipulated Date of Commencement October 01 2017
Stipulated Date of Completion /
Likely Date of Completion
November 30 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,999,277.00
Awarded for ₹ 1,963,600.00

Project highlights

Interior Furniture Works

 
Gallery Image
Contractors
M/s.Creation Interior Contractor
Gallery Image
Consultants
M/s. Rahul Deshpande & Associates
 
Similar Projects

See Similar Projects

Similar Project

Design and construction of bridge over river Satrem at Satrem, Sattari Taluka.

View Project
Similar Project

Construction of Bridge at Gaundali including approaches.

View Project
Similar Project

Hot mixing & Improvement of Internal Roads in V. P. St. Jose de Areal in Velim Constituency.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.