Status
100%
Completed
 
 

Sub Works

This project involved 3 sub works. The details of the same available below

1

Upgradation of Ward Nos.120, 123, 124, Staff Rest Rooms (Old Garage) and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa – Civil and plumbing works.

100% completed
 
Project Duration
Stipulated Date of Commencement January 28 2013
Stipulated Date of Completion /
Likely Date of Completion
February 28 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,00,41,753.00
Awarded for ₹ 3,90,22,573.00
Final Cost of Project ₹ 65,294,397.00
 
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
2

Electrical Works.

100% completed
 
Project Duration
Stipulated Date of Commencement May 26 2013
Stipulated Date of Completion /
Likely Date of Completion
February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 23,50,771.00
Awarded for ₹ 23,88,737.00
 
Contractors
M/s. Mohan Electricals
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
3

HVAC Works.

100% completed
 
Project Duration
Stipulated Date of Commencement September 26 2013
Stipulated Date of Completion /
Likely Date of Completion
February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,324,109.94
Awarded for ₹ 5,899,999.00
 
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd

See Similar Projects

Electrical work.

View Project

Construction of IInd phase of Goa Dental College & Hospital at Bambolim, Goa-Civil,Plumbing, internal electrical and fire fighting works-Balance work.

View Project

Restoration and Adaptive re-use of Old GMC.