Project Duration
Stipulated Date of Commencement
June 17 2006
Actual Date of Completion
October 14 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 118,993,540.00
Awarded for
₹ 135,678,880.00
Contractors
M/s. Eagle Construction Co.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd