Project Duration
Stipulated Date of Commencement September 01 2006
Actual Date of Completion May 15 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,777,629.00
Awarded for ₹ 1,798,714.00
Final Cost of Project ₹ 1,540,694.00

Project highlights

The building consists of 2 classrooms, staff room, toilets, etc.

 
Contractors
M/s. Sharadchandra H. Katkar, M/s. Sharadchandra H. Katkar
Consultants
M/s. Effective Architectural Services, M/s. Effective Architectural Services
 