Status
100%
Completed
 
 

Sub Works

This project involved 18 sub works. The details of the same available below

1

Construction of District Headquarters Office Building Complex for South Goa District at Margao, Salcete, Goa-Civil, Plumbing, Internal Electrical & Fire Fighting works

100% completed
 
Project Duration
Stipulated Date of Commencement December 21 2007
Stipulated Date of Completion /
Likely Date of Completion
April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 573,453,985.00
Awarded for ₹ 734,634,449.00
Final Cost of Project ₹ 977,494,975.00

Project highlights

Basement + Ground + 5 RCC framed structure

 
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
2

Lift work

100% completed
 
Project Duration
Stipulated Date of Commencement February 16 2010
Stipulated Date of Completion /
Likely Date of Completion
March 05 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,729,540.00
Awarded for ₹ 27,700,000.00
 
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
3

External Electrical works.

100% completed
 
Project Duration
Stipulated Date of Commencement February 16 2010
Stipulated Date of Completion /
Likely Date of Completion
March 10 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,33,96,780.00
Awarded for ₹ 21,149,474.00
 
Contractors
M/s. Imperial Engineering Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
4

Air conditioning works.

100% completed
 
Project Duration
Stipulated Date of Commencement June 16 2011
Stipulated Date of Completion /
Likely Date of Completion
March 25 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,57,17,757.00
Awarded for ₹ 23,604,023.00
 
Contractors
M/s. Manguirish Air Conditioning Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
5

Internal, external and special lighting fixtures (Part A – Supply of internal light fixtures / fans)

100% completed
 
Project Duration
Stipulated Date of Commencement September 15 2011
Stipulated Date of Completion /
Likely Date of Completion
February 28 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,27,37,030.00
Awarded for ₹ 9,146,323.00
 
Contractors
M/s. Eagle Construction Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
6

Audio Visual Equipments for conference system and AV room

100% completed
 
Project Duration
Stipulated Date of Commencement September 15 2011
Stipulated Date of Completion /
Likely Date of Completion
April 24 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,34,15,719.00
Awarded for ₹ 13,448,394.00
 
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
7

Telephone Exchange and UPS (Part A- UPS work)

100% completed
 
Project Duration
Stipulated Date of Commencement September 15 2011
Stipulated Date of Completion /
Likely Date of Completion
March 10 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 44,92,891.00
Awarded for ₹ 4,693,205.00
 
Contractors
M/s. Imperial Engineering Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
8

Telephone Exchange and UPS (Part B – IP Telephony and Video Conferencing work)

100% completed
 
Project Duration
Stipulated Date of Commencement February 01 2012
Stipulated Date of Completion /
Likely Date of Completion
March 16 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,00,26,362.00
Awarded for ₹ 5,637,190.00
 
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
9

Decorative Glazing for staircase blocks.

100% completed
 
Project Duration
Stipulated Date of Commencement April 22 2012
Stipulated Date of Completion /
Likely Date of Completion
March 15 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 87,89,272.80
Awarded for ₹ 8,250,144.00
Final Cost of Project ₹ 8,197,948.00
 
Contractors
M/s. R. S. Lawande
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
10

Carpentry and interior work.

100% completed
 
Project Duration
Stipulated Date of Commencement April 22 2012
Stipulated Date of Completion /
Likely Date of Completion
March 26 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,96,84,461.30
Awarded for ₹ 53,022,057.00
Final Cost of Project ₹ 55,689,522.00
 
Contractors
M/s.Concept Creator
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
11

Readymade furniture works

100% completed
 
Project Duration
Stipulated Date of Commencement July 09 2012
Stipulated Date of Completion /
Likely Date of Completion
May 27 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,28,94,732.00
Awarded for ₹ 37,798,417.00
Final Cost of Project ₹ 38,472,730.00
 
Contractors
M/s. Durian Industries Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
12

Internal, external and special lighting fixtures (Part B : External lights and façade lighting)

100% completed
 
Project Duration
Stipulated Date of Commencement August 11 2012
Stipulated Date of Completion /
Likely Date of Completion
March 15 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,09,68,986.00
Awarded for ₹ 6,849,960.00
 
Contractors
Shanti Electrical Enterprises Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
13

Supply of trees, grass, grass covers & allied material for landscaping works.

100% completed
 
Project Duration
Stipulated Date of Commencement January 17 2013
Stipulated Date of Completion /
Likely Date of Completion
April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,02,563.00
Awarded for ₹ 2,983,810.00
Final Cost of Project ₹ 2,794,242.00
 
Contractors
M/s. Vrindavan Agricultural Services
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
14

Signages work

100% completed
 
Project Duration
Stipulated Date of Commencement January 27 2013
Stipulated Date of Completion /
Likely Date of Completion
February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 43,59,583.00
Awarded for ₹ 4,023,779.00
Final Cost of Project ₹ 5,821,538.00
 
Contractors
M/s. Harshada Trading Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
15

Supply, installation, testing and commissioning of Precision AC, UPS, D. G. Set, Transformer, and related electrical works

100% completed
 
Project Duration
Stipulated Date of Commencement January 31 2013
Stipulated Date of Completion /
Likely Date of Completion
February 02 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,228,580.00
Awarded for ₹ 16,956,091.00
 
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
16

CPOE switches

100% completed
 
Project Duration
Stipulated Date of Commencement April 12 2012
Stipulated Date of Completion /
Likely Date of Completion
January 10 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ ----
Awarded for ₹ 1,539,900.00
 
Contractors
M/s. AGC Networks Limited
Consultants
Inhouse
17

Supply & Installation of Compactors in Record Room of Survey Department and Sub Civil Registrar.

100% completed
 
Project Duration
Stipulated Date of Commencement October 12 2013
Stipulated Date of Completion /
Likely Date of Completion
December 11 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,321,131.00
Awarded for ₹ 2,375,201.00
Final Cost of Project ₹ 2,269,824.00
 
Contractors
M/s. Kompress (India) Pvt. Ltd.
Consultants
Inhouse
18

Raising the Existing Compound Wall and Providing Additional Gutters

100% completed
 
Project Duration
Stipulated Date of Commencement October 16 2013
Stipulated Date of Completion /
Likely Date of Completion
March 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,002,100.00
Awarded for ₹ 4,991,914.50
Final Cost of Project ₹ 2,837,177.00
 
Contractors
M/s. A. Ponnuraj
Consultants
Inhouse

See Similar Projects

Beautification of Valpoi Town.

View Project

Repairs & Upgradation of Government Schools in the State of Goa: GHS –Mangoor Hill

View Project

Construction of High Court Complex at Penha de France, Porvorim-Civil,Plumbing,Electrical,Fire fighting, Lift and HVAC works.

View Project
x