Status
100%
Completed
Sub Works
This project involved 18 sub works. The details of the same available below
1
Construction of District Headquarters Office Building Complex for South Goa District at Margao, Salcete, Goa-Civil, Plumbing, Internal Electrical & Fire Fighting works
100% completed
Project Duration
Stipulated Date of Commencement
December 21 2007
Stipulated Date of Completion /
Likely Date of Completion April 30 2013
Likely Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 573,453,985.00
Awarded for
₹ 734,634,449.00
Final Cost of Project
₹ 977,494,975.00
Project highlights
Basement + Ground + 5 RCC framed structure
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
2
Lift work
100% completed
Project Duration
Stipulated Date of Commencement
February 16 2010
Stipulated Date of Completion /
Likely Date of Completion March 05 2013
Likely Date of Completion March 05 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,729,540.00
Awarded for
₹ 27,700,000.00
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
3
External Electrical works.
100% completed
Project Duration
Stipulated Date of Commencement
February 16 2010
Stipulated Date of Completion /
Likely Date of Completion March 10 2013
Likely Date of Completion March 10 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,33,96,780.00
Awarded for
₹ 21,149,474.00
Contractors
M/s. Imperial Engineering Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
4
Air conditioning works.
100% completed
Project Duration
Stipulated Date of Commencement
June 16 2011
Stipulated Date of Completion /
Likely Date of Completion March 25 2013
Likely Date of Completion March 25 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,57,17,757.00
Awarded for
₹ 23,604,023.00
Contractors
M/s. Manguirish Air Conditioning Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
5
Internal, external and special lighting fixtures (Part A – Supply of internal light fixtures / fans)
100% completed
Project Duration
Stipulated Date of Commencement
September 15 2011
Stipulated Date of Completion /
Likely Date of Completion February 28 2013
Likely Date of Completion February 28 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,27,37,030.00
Awarded for
₹ 9,146,323.00
Contractors
M/s. Eagle Construction Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
6
Audio Visual Equipments for conference system and AV room
100% completed
Project Duration
Stipulated Date of Commencement
September 15 2011
Stipulated Date of Completion /
Likely Date of Completion April 24 2014
Likely Date of Completion April 24 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,34,15,719.00
Awarded for
₹ 13,448,394.00
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
7
Telephone Exchange and UPS (Part A- UPS work)
100% completed
Project Duration
Stipulated Date of Commencement
September 15 2011
Stipulated Date of Completion /
Likely Date of Completion March 10 2013
Likely Date of Completion March 10 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 44,92,891.00
Awarded for
₹ 4,693,205.00
Contractors
M/s. Imperial Engineering Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
8
Telephone Exchange and UPS (Part B – IP Telephony and Video Conferencing work)
100% completed
Project Duration
Stipulated Date of Commencement
February 01 2012
Stipulated Date of Completion /
Likely Date of Completion March 16 2013
Likely Date of Completion March 16 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,00,26,362.00
Awarded for
₹ 5,637,190.00
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
9
Decorative Glazing for staircase blocks.
100% completed
Project Duration
Stipulated Date of Commencement
April 22 2012
Stipulated Date of Completion /
Likely Date of Completion March 15 2013
Likely Date of Completion March 15 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 87,89,272.80
Awarded for
₹ 8,250,144.00
Final Cost of Project
₹ 8,197,948.00
Contractors
M/s. R. S. Lawande
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
10
Carpentry and interior work.
100% completed
Project Duration
Stipulated Date of Commencement
April 22 2012
Stipulated Date of Completion /
Likely Date of Completion March 26 2013
Likely Date of Completion March 26 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,96,84,461.30
Awarded for
₹ 53,022,057.00
Final Cost of Project
₹ 55,689,522.00
Contractors
M/s.Concept Creator
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
11
Readymade furniture works
100% completed
Project Duration
Stipulated Date of Commencement
July 09 2012
Stipulated Date of Completion /
Likely Date of Completion May 27 2013
Likely Date of Completion May 27 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,28,94,732.00
Awarded for
₹ 37,798,417.00
Final Cost of Project
₹ 38,472,730.00
Contractors
M/s. Durian Industries Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
12
Internal, external and special lighting fixtures (Part B : External lights and façade lighting)
100% completed
Project Duration
Stipulated Date of Commencement
August 11 2012
Stipulated Date of Completion /
Likely Date of Completion March 15 2013
Likely Date of Completion March 15 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,09,68,986.00
Awarded for
₹ 6,849,960.00
Contractors
Shanti Electrical Enterprises Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
13
Supply of trees, grass, grass covers & allied material for landscaping works.
100% completed
Project Duration
Stipulated Date of Commencement
January 17 2013
Stipulated Date of Completion /
Likely Date of Completion April 30 2013
Likely Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,02,563.00
Awarded for
₹ 2,983,810.00
Final Cost of Project
₹ 2,794,242.00
Contractors
M/s. Vrindavan Agricultural Services
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
14
Signages work
100% completed
Project Duration
Stipulated Date of Commencement
January 27 2013
Stipulated Date of Completion /
Likely Date of Completion February 15 2014
Likely Date of Completion February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,59,583.00
Awarded for
₹ 4,023,779.00
Final Cost of Project
₹ 5,821,538.00
Contractors
M/s. Harshada Trading Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
15
Supply, installation, testing and commissioning of Precision AC, UPS, D. G. Set, Transformer, and related electrical works
100% completed
Project Duration
Stipulated Date of Commencement
January 31 2013
Stipulated Date of Completion /
Likely Date of Completion February 02 2014
Likely Date of Completion February 02 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,228,580.00
Awarded for
₹ 16,956,091.00
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
16
CPOE switches
100% completed
Project Duration
Stipulated Date of Commencement
April 12 2012
Stipulated Date of Completion /
Likely Date of Completion January 10 2013
Likely Date of Completion January 10 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ ----
Awarded for
₹ 1,539,900.00
Contractors
M/s. AGC Networks Limited
Consultants
Inhouse
17
Supply & Installation of Compactors in Record Room of Survey Department and Sub Civil Registrar.
100% completed
Project Duration
Stipulated Date of Commencement
October 12 2013
Stipulated Date of Completion /
Likely Date of Completion December 11 2013
Likely Date of Completion December 11 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,321,131.00
Awarded for
₹ 2,375,201.00
Final Cost of Project
₹ 2,269,824.00
Contractors
M/s. Kompress (India) Pvt. Ltd.
Consultants
Inhouse
18
Raising the Existing Compound Wall and Providing Additional Gutters
100% completed
Project Duration
Stipulated Date of Commencement
October 16 2013
Stipulated Date of Completion /
Likely Date of Completion March 15 2014
Likely Date of Completion March 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,002,100.00
Awarded for
₹ 4,991,914.50
Final Cost of Project
₹ 2,837,177.00
Contractors
M/s. A. Ponnuraj
Consultants
Inhouse
See Similar Projects
Beautification of Valpoi Town.
View ProjectRepairs & Upgradation of Government Schools in the State of Goa: GHS –Mangoor Hill
View ProjectConstruction of High Court Complex at Penha de France, Porvorim-Civil,Plumbing,Electrical,Fire fighting, Lift and HVAC works.
View Project