Project Duration
Stipulated Date of Commencement
March 04 2014
Actual Date of Completion
July 31 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 41,947,211.00
Awarded for
₹ 37,397,572.00
Final Cost of Project
₹ 34,928,883.83
Project highlights
Furniture work
Contractors
M/s. Amardeep Design
Consultants
M/s. Banaji & Associates