Project Duration
Stipulated Date of Commencement
May 18 2012
Actual Date of Completion
April 15 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 203,769,219.16
Awarded for
₹ 218,995,475.01
Final Cost of Project
₹ 234,576,304.00
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Banaji & Associates