Project Duration
Stipulated Date of Commencement
January 28 2013
Actual Date of Completion
February 28 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,00,41,753.00
Awarded for
₹ 3,90,22,573.00
Final Cost of Project
₹ 65,294,397.00
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd