Project Duration
Stipulated Date of Commencement
September 17 2023
Stipulated Date of Completion /
Likely Date of Completion January 15 2024
Likely Date of Completion January 15 2024
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,363,408.00
Awarded for
₹ 1,488,131.00
Project highlights
Supply, installation, testing and commissioning of UPS.
Contractors
M/s. Powertrac Corporation
Consultants
M/s. Frischmann Prabhu I Pvt. Ltd.