Project Duration
Stipulated Date of Commencement December 12 2011
Actual Date of Completion May 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,528,636.00
Awarded for ₹ 5,976,204.30
Final Cost of Project ₹ 7,053,881.00
 
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
 