Project Duration
Stipulated Date of Commencement
December 30 2023
Stipulated Date of Completion /
Likely Date of Completion March 29 2025
Likely Date of Completion March 29 2025
Status
10%
Completed
Cost (₹)
Estimated at
₹ 111,799,002.00
Awarded for
₹ 104,029,413.63
Project highlights
It includes
1) Ground floor consists of market, library store room, shops – 10 Nos, supermarket, panchayat store room.
2) Mezzanine consists of library panchayat office.
3) First floor consists of conference room, community hall, changing room, dining hall, toilet etc.
4) Parking facility for 2 wheelers and 4 wheelers.
Contractors
M/s. A.R.Constructions
Consultants
M/s. Rahul Deshpande & Associates
See Similar Projects
Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Interior and Allied Works
View Project
Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa .-CCTV works
View Project
Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa.- Audio Video (AV) Works.
View Project