Project Duration
Stipulated Date of Commencement
November 24 2023
Stipulated Date of Completion /
Likely Date of Completion February 23 2025
Likely Date of Completion February 23 2025
Status
15%
Completed
Cost (₹)
Estimated at
₹ 25,025,749.00
Awarded for
₹ 25,260,845.05
Project highlights
Stilt ground and 1st floor.
Multipurpose hall, shops, panchayat office and gym.
Contractors
M/s. V.Construct
Consultants
M/s. Banaji & Associates
See Similar Projects
Construction of Panchayat Building in Keri in Sattari Taluka.
View Project
Construction of Ravindra Bhavan at Canacona, Goa – Interior and furniture works.
View Project
Renovation of Ravindra Bhavan and construction of IInd phase of Ravindra Bhavan at Curchorem,Goa. -Road and Misc. Works
View Project