Project Duration
Stipulated Date of Commencement
March 19 2023
Stipulated Date of Completion /
Likely Date of Completion July 15 2024
Likely Date of Completion July 15 2024
Status
98%
Completed
Cost (₹)
Estimated at
₹ 24,838,299.00
Awarded for
₹ 27,062,739.87
Project highlights
Work includes Multi purpose Hall with Green rooms and attached toilets.
Contractors
M/s A. Y. Gulumkar
Consultants
M/s Creative Abode