Project Duration
Stipulated Date of Commencement
April 30 2016
Stipulated Date of Completion /
Likely Date of Completion July 29 2017
Likely Date of Completion July 29 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,312,759.00
Awarded for
₹ 14,422,515.20
Project highlights
The building is G+2 structure having Shops – 3 nos, post office, library, Self help group room along with toilets on ground floor, Panchayat office, Gym & toilets on first floor and hall along with dining and toilet facility on second floor.
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Bhaskar Wagle & Associates