Project Duration
Stipulated Date of Commencement December 13 2018
Actual Date of Completion December 18 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 456,100.00
Awarded for ₹ . 4,24,250.00
Final Cost of Project ₹ ? 500,615.00

Project highlights

providing and fixing of chairs, tables etc.

 
Contractors
M/s Manguesh enterprises
Consultants
M/s creative Abode
 