Project Duration
Start Date 21/06/2008
End Date 13/09/2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 126,506,209.00
Awarded for ₹ 172,960,669.00
Final Cost of Project ₹ 185,461,812.00

Project highlights

• Total built-up area: 6191.62 sq. m.

• Building consists of basement, ground floor and first floor

• Total no. of beds: 86 nos. [General Ward – Male : 20 nos., General Ward – Female : 20 nos., General Ward – Gynecology : 20 nos., Neonatal ward: 20 nos., Special Rooms (6 nos): 6 beds.

• Total no. of Operation Theatres: 02.

• 4 body Mortuary Cabinet : 01 no.

• Facilities provided:
• Basement (Area: 1095.76 sq.mts) : Canteen, equipment / store room, hospital store, electrical room, CSSD, changing rooms for gents & ladies staff, morgue, garbage collection, toilet facilities.

• Ground Floor (Area: 2558.21 sq.mts) : General ward (female), general ward (male), general ward (gynaecology) with nurses’ rooms & attached toilet blocks, 6 special rooms, linen store rooms for each ward, ultrasound, treatment room, examination room, x-ray, dark room, doctor’s room, ECG room, reception counter, waiting area & toilet facilities.

• First Floor (Area: 2537.65 sq.mts) : Registration counter, ENT, DOTS centre, skin specialist, general medicine store, pharmacy, waiting area, procedure room, immunization, dental, physiotherapist, pathologist room, laboratory, sample distribution & sample collection room, cabins for health officer & medical officer, administration block, neonatal ward with nurses room, cabin for neonatologist, sanitary inspector room, operation theatres, hall for anganwadi meetings & toilet facilities.

• Building is provided with lift, connecting ramps, air conditioning and medical gases facilities.

 
Contractors
M/s M V Roa Infra Projects Pvt Ltd
Consultants
M/s Effective Architectural Services
 

Additional Work

This project involved 8 additional tasks. The details of the same available below

Status Progress Project Duration
Start Date / End Date
Cost (Rs.)
Estimated / Awarded
Consultants & Contractors
1 Lift work.
100% completed
 
 

19/02/2010 - 19/02/2014

 

₹ 3,316,000.00 / ₹ 3,432,000.00

  M/s Effective Architectural Services
- M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
2 Electrical & Fire Fighting work.
100% completed
 
 

16/07/2010 - 19/02/2014

 

₹ 14,521,313.00 / ₹ 13,783,266.21

  M/s Effective Architectural Services
- M/s. Sunshine Electric Co. Pvt. Ltd.
3 Air Conditioning work
100% completed
 
 

25/12/2010 - 19/02/2014

 

₹ 35,88,688.00 / ₹ 2,999,999.00

  M/s Effective Architectural Services
- M/s. Aprant Motors Pvt. Ltd.
4 False ceiling works.
100% completed
 
 

02/07/2010 - 31/12/2013

 

₹ 3,064,138.00 / ₹ 2,909,220.00

  M/s Effective Architectural Services
- M/s. Deshpande Constructions
5 STP & ETP works
100% completed
 
 

10/06/2011 - 31/12/2013

 

₹ 3,480,506.00 / ₹ 2,884,300.00

  M/s Effective Architectural Services
- M/s. Sainath Enviro-Tech
6 Medical Gas & Steel OT work.
100% completed
 
 

04/09/2011 - 19/02/2014

 

₹ 19,288,538.00 / ₹ 16,775,440.00

  M/s Effective Architectural Services
- M/s. MDD Medical Systems (I) Pvt. Ltd.
7 Furniture works.
100% completed
 
 

12/09/2012 - 25/09/2013

 

₹ 16,433,755.00 / ₹ 16,248,000.00

  M/s Effective Architectural Services
- M/s. Floor Space
8 Motruary Cabinet Works
100% completed
 
 

21/01/2013 - 19/02/2014

 

₹ 411,664.00 / ₹ 492,000.00

  M/s Effective Architectural Services
- M/s. Megastar Engg., Pune

See Similar Projects

Face-lift to Tisk Usgao Hospital building including staff quarters

View Project

Construction of District Hospital at Mapusa, Goa

View Project

Supply, installation, testing and commissioning of Central Air Conditioning System for GMC Complex at Bambolim, Goa.

View Project
x