Project Duration
Stipulated Date of Commencement
May 31 2023
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
85%
Completed
Cost (₹)
Estimated at
₹ 27,073,347.00
Awarded for
₹ 23,436,764.00
Project highlights
Providing 100 KLD STP for Hospital Premises along with allied Civil works.
Contractors
M/s. Concept Creator
Consultants
M/s. Saolapurkar and Associates