Project Duration
Stipulated Date of Commencement January 17 2014
Stipulated Date of Completion /
Likely Date of Completion
March 17 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,730,000.00
Awarded for ₹ 2,080,000.00
 
Gallery Image
Contractors
M/S. ELITE
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 