Project Duration
Stipulated Date of Commencement
July 10 2004
Stipulated Date of Completion /
Likely Date of Completion October 15 2004
Likely Date of Completion October 15 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 76,400,000.00
Awarded for
₹ 40,155,000.00
Project highlights
Supply of cables
Contractors
M/s. Electro Engineering Enterprises
Consultants
M/s. TPF Engineering Pvt. Ltd.