Project Duration
Stipulated Date of Commencement
July 04 2017
Stipulated Date of Completion /
Likely Date of Completion October 02 2017
Likely Date of Completion October 02 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 31,630,179.00
Awarded for
₹ 28,239,715.00
Project highlights
Supply, Installation, Testing and Commissioning of street light poles and fixtures
Contractors
M/s. Prabhu Enterprises
Consultants
M/s LKS India Pvt. Ltd.