Project Duration
Stipulated Date of Commencement
August 04 2023
Stipulated Date of Completion /
Likely Date of Completion December 30 2023
Likely Date of Completion December 30 2023
Status
Completed
Cost (₹)
Estimated at
₹ 5,083,848.28
Awarded for
₹ 4,015,655.00
Project highlights
The scope of work includes Supply Installation, Testing and Commissioning of Central Sterile Services Department(CSSD) Equipments
Contractors
M/s. Genist Technocracy
Consultants
M/s. Saolapurkar and Associates