Project Duration
Stipulated Date of Commencement March 08 2019
Actual Date of Completion August 07 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,604,390.00
Awarded for ₹ 21,378,699.00
Final Cost of Project ₹ 21,378,699.00

Project highlights

up- gradation of the existing Laboratory facilities

 
Contractors
M/s. Bioxia
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Strengthening of existing food & drugs laboratory under Directorate of Food & Drugs Administration Block at Bambolim Complex, Bambolim Tiswadi – Goa SH: Upgradation of the Microbiological section.

100% completed
 
Project Duration
Stipulated Date of Commencement September 07 2018
Stipulated Date of Completion /
Likely Date of Completion
November 22 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 9,605,962.41
Awarded for ₹ 97,86,999.00
Final Cost of Project ₹ 9,786,999.00

Project highlights

up- gradation of the existing Laboratory facilities

 
Contractors
M/s. Bioxia
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.

See Similar Projects

Construction of new building for SCERT at Porvorim, Goa – Supply, Installation, Testing & Commissioning of Audio Visual equipments

View Project

Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-BicholimTaluka-Package E (G.P.M.S. Nanoda, G.P.M.S. Advalpal, G.P.S. Amthane)

View Project

External Development Work

View Project
x