Project Duration
Stipulated Date of Commencement
June 10 2011
Actual Date of Completion
December 31 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,480,506.00
Awarded for
₹ 2,884,300.00
Final Cost of Project
₹ 3,448,590.00
Project highlights
Sewage and effluent treatment facility
Contractors
M/s. Sainath Enviro-Tech
Consultants
M/s Effective Architectural Services