Project Duration
Stipulated Date of Commencement
December 23 2005
Stipulated Date of Completion /
Likely Date of Completion February 10 2006
Likely Date of Completion February 10 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,792,027.00
Awarded for
₹ 3,657,495.60
Project highlights
Includes hard landscape elements such as paved areas, planter boxes, fences, walkways, pathways, tanks, etc. and soft landscaping elements such as providing and fixing / planting lawns, shrubs, plants, trees and other landscape finishes.
Contractors
M/s. Hariyalee Nursery
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
See Similar Projects
Construction of 500 Bedded District Hospital At Margao, Goa – LV System
View Project
Air Conditioning work
View Project
Renovation/Maintenance of Hospitals, CHC’s, PHC’s, RMD’s under Directorate of Health Services in North Goa – S.H. Replacement of phase barrier sheets in HT panel of Megawin make and one time servicing of 33 KV HT outdoor breaker installed at Sub District Hospital, Ponda – Goa
View Project