Project Duration
Stipulated Date of Commencement
December 23 2005
Actual Date of Completion
April 30 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,792,027.00
Awarded for
₹ 3,657,495.60
Final Cost of Project
₹ 3,894,475.00
Project highlights
Includes hard landscape elements such as paved areas, planter boxes, fences, walkways, pathways, tanks, etc. and soft landscaping elements such as providing and fixing / planting lawns, shrubs, plants, trees and other landscape finishes.
Contractors
M/s. Hariyalee Nursery, M/s. Hariyalee Nursery
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd