Project Duration
Stipulated Date of Commencement February 26 2014
Actual Date of Completion October 13 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,09,75,951.00
Awarded for ₹ 2,44,73,933.00
Final Cost of Project ₹ 26,896,657.00

Project highlights

Repairs and upgradation of Govt High school Malkarne and Govt. High school Balli

 
Contractors
M/s K G Thomas, M/s K G Thomas
Consultants
Shri Manoj M. Amshekar,
 