Project Duration
Stipulated Date of Commencement
August 23 2018
Stipulated Date of Completion /
Likely Date of Completion September 06 2019
Likely Date of Completion September 06 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,557,021.00
Awarded for
₹ 12,865,535.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. Sandeep R S Khandeparkar
Consultants
M/s. Datta Kare
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Sattari Taluka : Package-K (GHS Sawardem, GPS Tem Uste, GPS Massordem, GPS Velus, GPS Sawantwada Pal, GPS Sawardem)
View Project
Construction of Government Primary School, Toncawada, Jua, St. Estevam in Tiswadi Taluka.
View Project
Repairs/ Upgradation & Mainrenance ofGovemment Schools in the State ofGoa – Civil, Plumbing & Electrical works – Package – III (Tiswadi & Ponda Taluka) [Also falls in Ponda, St. Andre, Panaji and Cumbarjua]
View Project